Clean Rivers Project · 18 miles of tunnel

The tunnels worked. We can show you by how much.

DC Water is spending billions boring storage tunnels under the city to stop sewage reaching the rivers. The Anacostia's are finished, so for the first time there is enough data to say whether the idea works.

How a storage tunnel stops an overflow

A combined sewer overflows because rain arrives faster than the pipes can carry it to Blue Plains. You can fix that by making the pipes bigger, by keeping rain out of them, or by holding the water somewhere until the storm passes. The Clean Rivers Project mostly does the third.

The tunnels are enormous — 23 feet in diameter, up to 160 feet underground. During a storm, combined flow that would have spilled into the river drops into the tunnel instead. Afterwards, pumps lift it back out and send it to Blue Plains for treatment at a rate the plant can handle.

Nothing is treated in the tunnel. It is storage, not treatment. The benefit is entirely about timing: it converts a burst the system cannot handle into a steady flow it can.

What happened to the Anacostia

The Anacostia tunnels came online in stages, the largest — Northeast Boundary — in September 2023. The effect is not subtle.

  • Anacostia
  • Potomac
  • Rock Creek
Anacostia 2005 3,387 million gallons of sewage overflow
Anacostia 2025 5.4 million gallons — a 99.8% reduction
Overflow events 417 → 3 per year, 2005 vs 2025
Decree allowance 10× better than the target requires

The Anacostia has already beaten the target it was given for 2030 — and beaten it by an order of magnitude, five years early.

Was it just dry weather?

A fair question, and the one that decides whether the money worked. Overflow volume swings with rainfall, so a run of quiet years could produce the same picture.

It was not the weather. Measured as gallons spilled per inch of storm rain — the measure that best predicts overflows — the Anacostia is down 90%, essentially identical to the raw figure. Rainfall across the two eras was almost the same: 41.1 inches a year before, 42.3 after.

In the sharpest form: in 2005 the Anacostia received 76 million gallons of overflow for every inch of rain. In 2025 it received 0.15.

How the rainfall adjustment works →

Why the Potomac has not changed

Because its tunnel is not built yet. The Potomac River Tunnel is under construction with a deadline of March 2030. Until then the Potomac's combined sewers behave much as they did in 2005.

That has an awkward consequence. As the Anacostia improved, the Potomac did not — so the share of DC's remaining sewage overflow that goes into the Potomac has risen from 31% to about 75%. The city's overflow problem did not so much shrink as relocate.

The 2030 date has already moved once. The original decree required everything finished by 2025. A 2015 amendment pushed it to 2030, on affordability grounds, over the objection of the environmental groups who brought the original lawsuit. Full timeline →

Where the money went

Major Clean Rivers components
ComponentWatershedStatus
Blue Plains TunnelAnacostia / Potomacin service
Anacostia River TunnelAnacostiain service 2018
Northeast Boundary TunnelAnacostiain service Sept 2023
Poplar Point Pumping StationAnacostiain service Mar 2018
Piney Branch improvementsRock Creekin service May 2018
Rock Creek green infrastructureRock Creekin construction
Piney Branch TunnelRock Creekin construction
Potomac River TunnelPotomacdue 2030

The 2015 amendment also changed the method for the Potomac and Rock Creek, allowing green infrastructure — rain gardens, permeable paving, anything that keeps rain out of the combined sewer in the first place — to substitute for part of the tunnel capacity.

Status dates from DC Water's quarterly consent decree status reports, 2005–2026. Overflow figures from the quarterly CSO operations reports. All sources and datasets →